Entering Task Information in Microsoft Project - Continued
For this exercise we will use the task area of the Gantt view to enter our
tasks. Assuming you have a blank, new project, select the first row of the
project.
- Project Office and press enter.
- Scope and press enter.
- Determine Project Office Scope and press tab, enter 3 days for the
duration and press enter. Press left arrow once.
- Document high-level Project Office requirements including resources, press
tab, enter 2 day for the duration and press enter. Press left arrow once.
- Justify Project Office via business model, press tab, enter 3 days for the
duration and press enter. Press left arrow once.
- Secure Executive sponsorship, press tab, enter 2 days for the duration,
press enter and press left arrow once.
- Scope Complete, press tab, enter 0.
- Your screen should look like the one below.

As this point we haven't entered any of the tasks dependencies, recourses or
rolled anything up into major task headings; we'll do these next.
Note: Any tasks that is created without a duration is a milestone.
|
The Principles Of Project Management - Free 66 Page Preview!: Every project you
manage will be unique. Scope, budgets, team dynamics, and timeframes will differ. As a project manager, the most important factor in achieving project
success will be your understanding of 'The Principles Of Project Management'. This book will show you that project management isn't rocket science.
Outsourcing Web Projects: 6 Steps to a Smarter Business - Free Preview!: Outsourcing Web
Projects: 6 Steps to a Smarter Business provides you with tried and tested techniques that will ensure that you can deliver complex, high quality web
projects using outsourced development resource, both on time and on budget!
|