Assigning Project Resources using Task Spreadsheet in Microsoft Project

Now that we have created some resources for our project, we can go back as assign tasks to these resources. There are a number of ways to do this and we'll cover the two most common. In this section we'll discuss using the Task Spreadsheet of the 'Gantt View' of Microsoft Project.

  1. Click on 'Gantt Chart' in the left-hand toolbar.
  2. Select row 3 and tab to the end column marked 'Resources'.
  3. From the drop-down dialog box, select 'Corporate Management'.
  4. Repeat this for all other tasks in the project.
  5. Since these tasks will have more than one resource assigned we'll need to assign the other resources from the 'Task Information' dialog box.

Your project should now look like the following:

Microsoft Project

<Creating Resources Assigning Resources Dialog >

 The Principles Of Project Management - Free 66 Page Preview!: Every project you manage will be unique. Scope, budgets, team dynamics, and timeframes will differ. As a project manager, the most important factor in achieving project success will be your understanding of 'The Principles Of Project Management'. This book will show you that project management isn't rocket science.

Outsourcing Web Projects: 6 Steps to a Smarter Business - Free Preview!: Outsourcing Web Projects: 6 Steps to a Smarter Business provides you with tried and tested techniques that will ensure that you can deliver complex, high quality web projects using outsourced development resource, both on time and on budget!